Exciting developments at Derwent Bank

As part of our continued commitment to enhance our property and service, we are thrilled to advise you that we are undertaking an exciting 6-month renovation project on both our public and external areas around Derwent Bank. This will include the construction of a beautiful new orangery, new accommodation for our leaders and house team plus eight new guest bedrooms in the grounds to replace the old chalets. It was essential for the longevity of Derwent Bank that we tackled all these issues especially those effecting the welfare of our team.

Project scope

It was recognised a few years ago that there were a number of buildings at the house that were no longer fit for purpose and needed to be changed. They included, the Managers house, the team accommodation, the conservatory and the chalet block.

As well as the four main areas above there are several other structural issues that needed addressing including improving the electric supply, restoring the chimney above the conservatory, replacing the sewage system and moving the bar.

The process

A project team that included a Planning Consultant, an Architect, a Quantity Surveyor plus a team from HF Holidays has progressed the project. We have also engaged a local building firm to help us bring the scheme alive. As part of Phase 1, our existing conservatory has already been dismantled. During this time, our guests will be able to make full use of our selection of board games, magazines and a cosy fireplace in our lounge as well as our well stocked bar.

The outcome

Once all completed, we will have added three new buildings to the Derwent Bank site plus a number of smaller improvements throughout the site.

Plans for refurbishment at HF Holidays' Derwent Bank

Garden rooms

Concept for the new Garden Rooms at Derwent BankThe Garden rooms replace the chalets that were located to the side of the main house. The new building will contain eight bedrooms compared to the five rooms in the chalet block.

The foot print of the building is slightly bigger however the significant change is its now a two-storey building with four bedrooms along the bottom rather than five ground floor rooms. This gives the bedrooms a bigger footprint plus their own courtyard or balcony facing towards the lake.

Concept for the new Garden Rooms at Derwent BankThe building has a direct link to the new Orangery which removes the need for the guests to walk around the front of the house to get in. It also has a direct link to the boot room. Both paths give the feeling of connection to the main house.

 

 

The Orangery

Concept for the new Orangery at Derwent BankThe Orangery will be located in the corner of the house where the old conservatory stood. It will have bifolding doors that open up to a raised patio area overlooking the gardens and lake.

Underneath the patio will be the maintenance storage area and bar cellar. As part of the design we have put in the provision to relocate the bar to the middle lounge. The purpose of this move is to put the bar/social space in the middle of the house and closer to the restaurant rather then being at one end. Our plan is to make this change in 2020.

Timings

Below are the key timing of the build projects. We have built in some bad weather contingency to each timescale.

Build area

Build start date

Build end date

Available to guests

Leader & Manager House

5 November 2018 1 April 2019 1 April 2019

Orangery

19 November 2018 1 March 2019 1 March 2019

Garden Rooms

21 November 2018 1 May 2019 1 June 2019

Guest disruption

As you can see, there will be building work happening while guests are in the house. Our aim is to keep disruption to a minimum so that they enjoy their holiday with us.

  1. Festive Guests: The Orangery won’t be available for our festive guests. The building company will put in a temporary covered walkway linking the corridor to the restaurant. This will reduce the amount of public space available during the festive holidays.
  2. Reopening: The Orangery will reopen for guest use on 1 March. This is just after the reopening of the house on the 15 February. At this stage guests will be able to access the restaurant via the side door just past the office.

We are conscious that we will have guests in the house while the garden rooms and the new houses are being built. We have a number of measures in place to prevent disruption, they include:

  • Restricted building time – building work between the hours of Monday to Friday, 8am and 5.30pm and Saturdays from 8am until 1pm. Looking at the build programme we believe that most of the noisy garden room work will be completed by 1 March.
  • Health and Safety – some areas of the grounds will be fenced off from team and guests. At times this will affect the coach pick up location however this will be managed at a local level by the house team.

    There will be construction traffic using the bottom drive entrance which is located next to the Coach house. We will encourage guests and delivery vehicles to use the carpark entrance to reduce the any risk or any delay in getting on to site.
  • Dust – we’ve arranged for regular road sweeping to take place to reduce the amount of dust that will be generated.
  • New house build – the build programme for the new houses is out of our control however they need to follow the building timing detailed above and the build most be completed by August 2020

    As part of the Transfer of Deeds (selling of the land) we have added a number of clauses regarding external building finishing to ensure it is in keeping with the local environment and the finishing does not diminish our guest experience.

Every effort has been made to minimize the impact on you during your stay and we apologize for any inconvenience during the house makeover. We sincerely appreciate your understanding while we make these improvements to the house and thank you for your continued support during this time.

The POD

In the grounds of Derwent Bank, we have located our experimental POD for testing. The POD is designed to sleep 2 but can accommodate a family of 4. It comes fully equipped with underfloor heating,bathroom, Wi-Fi, TV and is fully furnished. We’re still tweaking it and we hope to have guests staying in it next season.

The exterior of the new POD at Derwent Bank The interior of the new POD at Derwent Bank


Plan your visit to Derwent Bank in the Northern Lake District in 2019 to view the changes for yourself! >

Sign up for our newsletter

Our newsletters are a great way to receive special offers, inspiring articles, stories and news from HF Holidays.

To subscribe, please enter your email address below and click 'submit'.

We won't pass your details on to any third party unless we have your express permission, you are free to unsubscribe at any time.